The light rail construction work right now

Keep updated on the light rail construction work in the municipality of Lyngby-Taarbæk right now.

In Lyngby-Taarbæk the light rail construction work is devoted into four areas: Buddingevej, Lyngby Centrum, Klampenborgvej and Lundtoftegårdsvej/DTU.

Read more about the areas below. This site is monthly updated.

Letbane - torvet efterår 2021
Letbane - torvet efterår 2021
  • Buddingevej

    At Buddingevej the light rail construction work is currently going on between the viaduct (under the S-train line) and the municipal boundary.

    Travellers vil face inconvenience as the road works affects the car traffic, pedestrians and cyclists.  

    From ultimo January 2023 to March 2023 access and exit ramps to M3/Buddingevej exit 19 will be closed.

    Arbejdsområder på Buddingevej
    Arbejdsområder på Buddingevej

    1: From the viaduct to Engelsborgvej

    • The work in the eastern side of Buddingevej is expected to be completed in mid-2023.
    • Here a new tunnel for pedestrians is built next to the existing one for cars and busses.
    • During the period there will be traffic diversions due to road work in the intersection at Buddingevej/Engelsborgvej. 

    2: The intersection at Engelsborgvej

    • The work in the intersection will be done from February 2023 to medio 2023.
    • It is not possible to drive through the intersection from Engelsborgvej.
    • Engelsborgvej (O4) is the only access route through the tunnel.
    • There will remain access only for residents, daily garbage collection and emergency services.
    • There will remain access to houses on both sides of Buddingevej.
    • The cycle path is two-way in the eastern side of Buddingevej.

    3: From Engelsborgvej to Chr. X's Allé

    • The work on the western side of Buddingevej is expected to be done in Spring 2023.
    • There will remain access only for residents, daily garbage collection and emergency services.
    • There will remain access to houses on both sides of Buddingevej.
    • The cycle path is two-way in the eastern side of Buddingevej.

    4:The intersection at Chr. X's Allé

    • The work in the intersection will be done from January 2023 to medio 2023.
    • The traffic is two-way through the intersection.
    • The traffic between Chr. X's Allé and Nybrovej is one-way to the south.
    • The cycle path is two-way in the eastern side of Buddingevej.

    5: From Chr. X's Allé to Nybrovej

    • The work on the eastern side of Buddingevej will be done medio 2023.
    • The traffic between Chr. X's Allé and Nybrovej is one-way to the south.
    • There will remain access to houses on both sides of Buddingevej.
    • The cycle path is two-way in the eastern side of Buddingevej.

    6: The intersection at Nybrovej

    • The work in the intersection will be done from primo January 2023 to medio 2023.
    • There will be limited traffic on Nybrovej (towards Gentofte).
    • The traffic is directed via Gammelmosevej and Sandtoften.

    7: From Nybrovej to Fort Allé (the municipality boarder)

    • The work is expected to be done medio 2023.
    • The traffic between Nybrovej and Fort Allé is two-way and there is no parking on Buddingevej.
    • The cycle path is two-way in the eastern side of Buddingevej.
    • There will remain access to houses on the western side of Buddingevej.
  • Centre of Lyngby

    The Greater Copenhagen Light Rail is working in the Centre of Lyngby and the road work is affecting the car traffic, pedestrians and cyclists.

    We therefore recommend you to search for alternative routes: orange (from Copenhagen to Centre of Lyngby + From Centre of Lyngby to Kongevejen), blue (from Kongevejen to Centre of Lyngby + from Centre of Lyngby to Copenhagen + from Centre of Lyngby to Buddingevej), purple (bus from Centre of Lyngby to Buddingevej)

    Arbejdsområder i Lyngby C
    Arbejdsområder i Lyngby C

    1: Jernbanepladsen

    • The construction work is expected to be done in the summer 2023.
    • The light rail station is being built here and due to that the traffic to/from Jernbanepladsen is affected.
    • New driving lanes and light rail tracks are being established at Lyngby Station.
    • The bus routes from Lyngby Station will be rescheduled for a longer period.

    2: Lyngby Hovedgade / Klampenborgvej

    • The work in the intersection is expected to be done in the spring 2023.
    • In the intersection new signal systems will be established.

    3: Klampenborgvej (Lyngby Storcenter - Magasin)

    • The construction work will last until spring 2023.
    • Klampenborgvej has been permanently closed for car traffic from Lyngby Hovedgade to Kanalvej. On this section a new urban space will be established.
    • There will remain access to parking under Lyngby Storcenter.

    4: The intersection at Klampenborgvej / Kanalvej

    • The construction work in the intersection will be done in the spring 2023.
    • The traffic on Kanalvej will remain two-way.
    • The parking ramp from the basement under Lyngby Storcenter to Klampenborgvej will be closed for a shorter period.
    • While working in the intersection Kanalvej will be extended and this work is also expected to be done in mid-2023.
  • Klampenborgvej

    The Greater Copenhagen Light Rail is working multiple places at Klampenborgvej which affects both the car traffic, pedestrians and cyclists.

    Statusrappport Klampenborgvej feb 23
    Statusrappport Klampenborgvej feb 23

    1: From Kanalvej to Firskovvej

    • One-way traffic is possible from Firskovvej to Kanalvej. There will remain acces for pedestrians and cyclists.
    • Busses and car traffic are driving via Sorgenfrigårdsvej and Firskovvej instead of Kanalvej-Klampenborgvej.
    • Furthermore the bridge under Nærum Lokalbane is being reinforced and the driving lanes from Kanalvej to Firskovvej are being expanded. 

    2: From Firskovvej to Lundtoftegårdsvej

    • The construction work will be done from March 2021 until mid-2023.
    • During this period there will among other things be done a changing from four driving lanes to two driving lanes, so there will be space for the light rail (in the side of Klampenborgvej nearest Circle K).

    3: Klampenborgvej/Firskovvej

    • The work in the intersection is expected to be done medio 2023.
    • The traffic is directed via Firskovvej and Klampenborgvej.

    4: Klampenborgvej/Sorgenfrigårdsvej

    • The work in the intersection is expected to be done in the spring 2023.
    • The work here is depending on the work in the intersection at Lyngbygårdsvej.
  • Lundtoftegårdsvej/DTU

    The work is coordinated between The Greater Copenhagen Light Rail, DTU and Movia.

    Statusrapport Lundtoftegårdsvej feb 23

    1: Lundtoftegårdsvej

    • The construction work will be done medio 2023.
    • The work contains of
      • An expansion of the intersection at Circle K Lyngbygårdsvej/Lundtoftegårdsvej
      • The western side of Lundtoftegårdsvej will be prepared for establishing the light rail. Due to this the intersection at Lyngbygårdsvej will be closed for a period.
      • The access to/from Kornagervej is being permanently closed in July 2022.

    2: Lundtoftegårdsvej

    • Here will be established a stormwater pool in the area between Lundtoftegårdsvej and Helsingørmotorvejen.
    • This work is expected to be done mid-2023.

    3: Lundtoftegårdsvej

    • At the corner Lundtoftegårdsvej/Akademivej the housing company KAB are building family and student apartments. These are expected to be done in spring 2023.

    4: Akademivej / Asmussens Allé

    • The construction work in this area is expected to last from January 2022 until medio 2023.
    • The light rail will run in the southern side of Akademivej which at the same time means that the intersection Akademivej/Kollegiebakken is being rebuilded.
    • A light rail station at Akademivej is being built.

    5: Asmussens Allé / Anker Engelunds Vej

    • The construction work in this area is expected to last from autumn 2022 to spring 2023.
    • In this period Anker Engelundsvej (from Asmussens Allé to Lundtoftegårdsvej) is closed. Alternative route via Akademivej and Lundtoftevej.
    • The work includes among other things reinforcement of tunnels and expansions of the road (Anker Engelunds Vej).
    • The road will be expanded and a light rail station at Anker Engelunds Vej will be established

    6: Lundtoftegårdsvej 

    • The construction work in this area is expected to last from September 2021 until ultimo 2022.
    • The light rail trails will run alongside Helsingørmotorvejen.
    • Here will be built light rail stations at Rævehøjvej and Lundtofte.

    7: Lundtoftegårdsvej / Anker Engelunds Vej

    • The work here is expected to be done from spring 2023 until medio 2023. 
    • Here the light rail will be established as well as signal system.
Light rail time line in english
Light rail time line in english